LRT-1 Cavite Extension operations likely in Q4

LIGHT Rail Transit (LRT) Line 1 Cavite Extension Phase 1 is expected to begin operations in the fourth quarter of 2024.

Light Rail Manila Corp. (LRMC) on Wednesday said the project was 97 percent complete as of January, solidifying the firm's target opening and operations in Q4.

«We are optimistic about the progress achieved in the LRT-1 Cavite Extension Phase 1 project. This significant milestone is a testament to the perseverance and dedication of our team and our contractors, all working together to make this project come to life, connecting countless residents in the south of Metro Manila and nearby provinces,» Juan Alfonso, LRMC president and chief executive officer, said.

Both civil and system works are progressing rapidly to ensure a smooth and timely opening.

The five new stations are nearing completion, with the Redemptorist Station at 93.3 percent, MIA Station at 93.5 percent, Asia World Station at 83 percent, Ninoy Aquino Station at 88 percent, and Dr. Santos Station at 94.1 percent.

Simultaneously, system works are progressing efficiently. Telecom installation activities at Dr. Santos and Redemptorist stations have been completed, and similar work has begun at MIA and Asia World stations.

Also, LRMC is actively conducting test runs of various generations of LRT-1 trains, ensuring their compatibility and readiness for operations.